FY 07 Project Status Update

  1. Develop RFP for Technical Assistance / Select Consultants Completed
  2. Secure Executive Oversight Committee (EOC) Guidance Completed
    • Scope
    • Project Management Structure (Teams/Representation)
    • Budget
    • Timeline
  3. Initiate Project Team assignments Completed
  4. Commence work planning Completed
  5. Secure University BOT approval for consultants Completed
  6. Conduct parallel processes Completed
    • Gather requirements
    • Assess technical environment (current architecture)
  7. Merge findings for identification of gaps Completed
  8. Gap analysis Completed
  9. Research possible solutions & costs Completed
  10. Validate possible solutions against requirements Completed
  11. Deliver findings to EOC Completed